Well-known member
Look all in. Looks like the extent of the cutting is done and the majority of the trail should be clear of towers up to where the current top of Upper Comp began.
Welcome to AlpineZone, the largest online community of skiers and snowboarders in the Northeast!
You may have to REGISTER before you can post. Registering is FREE, gets rid of the majority of advertisements, and lets you participate in giveaways and other AlpineZone events!
Look all in. Looks like the extent of the cutting is done and the majority of the trail should be clear of towers up to where the current top of Upper Comp began.
I can see 9 (9th is at the top and a bit out of focus but can clearly make out the crossarm and lifting frame). Could be one below the lowest in the frame as well just off the base terminal (actually, that one is quite likely). So 10, perhaps 11. I wouldn't say that's a shocker, modern detaches seem to have many fewer towers today than 20-25 years ago.Am I correct in seeing only 8 towers in view?? I'm sure there'll be some small ones at the top and bottom terminals but doing that line with about 10 towers is VERY impressive. I wonder if they (engineering/dopp) went aggressive with the profile as on a windy day the existing quad is extremely wind protected.
There would be a couple more at the very top that are unseen out of the field of vision. We can't see the breakover really.Am I correct in seeing only 8 towers in view?? I'm sure there'll be some small ones at the top and bottom terminals but doing that line with about 10 towers is VERY impressive. I wonder if they (engineering/dopp) went aggressive with the profile as on a windy day the existing quad is extremely wind protected.
Went by Berkshire East today to check on new lift install because I thought I saw something at the edge of the base cam. Sure enough lower terminal and shed are in place ! Also happy to report that the potholes on the bridge over the Deerfield River have been patched.
View attachment 59407
View attachment 59408
Still sitting in parking lot :
View attachment 59410
I love the one random fan gun that is placed near the base of the lift. Hope springs eternal I guess!Went by Berkshire East today to check on new lift install because I thought I saw something at the edge of the base cam. Sure enough lower terminal and shed are in place ! Also happy to report that the potholes on the bridge over the Deerfield River have been patched.
View attachment 59407
Still sitting in parking lot :
Summit cams went down late last week, the last shot they got was of heavy equipment and electrical trucks being up at the summit. I imagine that the top terminal went on over the weekend and haul rope will probably be sometime next week.Snowmaking has begun … still no sign of haul rope installation. Upper mountain cameras have been offline for several days, I think they are doing electrical work on the new summit terminal.
View attachment 59526
Photos from the weekend: Work Continues on Berkshire East High Speed Quad - NewEnglandSkiIndustry.comSummit cams went down late last week, the last shot they got was of heavy equipment and electrical trucks being up at the summit. I imagine that the top terminal went on over the weekend and haul rope will probably be sometime next week.
Thanks for posting, nice to see some pictures of what’s going on at the summit. Not sure about the name “T-Bar Express” though, too generic. Too bad “Berkshire Express” is already being used by JiminyPhotos from the weekend: Work Continues on Berkshire East High Speed Quad - NewEnglandSkiIndustry.com