Black replacement with the Black Quad has been approved by VT finally! Congrats!
Sent from my SM-T830 using AlpineZone mobile app
VT Act 250: Replacement of the existing Black Chair lift. Project components include: removal of the existing fixed-grip triple chairlift, towers, top and bottom terminals, operator buildings and associated infrastructure. Installation of a new fixed-grip quad chairlift including towers, top and bottom terminals, operator buildings, and associated infrastructure. The proposed new chair alignment will be moved slightly east, ranging from a 25' offset at the bottom to 50' at top, in the existing trail routing to accommodate trajectory of the new chair and establishment of a new top terminal approximately 400' beyond existing.
Looks like Do Work will go right from Ski area ops to lift construction.
Oh, and don't forget about the pond - that permit is pending but will likely be another project underway.
The Magic momentum is monumental.....