Highly disagree with everything you say up here. What about buying a used Tbar. Also the run is not that long. You can do it for less that $1M. And when the line at Gate house is 20+ minutes long which it has been all year long this year, that T-Bar would not be the most popular lift to get to you slidebrook or North links? You are wrong. That is very logistical and totally worth it.
There are very few if any used decent T-Bars available to acquire and re-install. Most of them are old Halls sitting on NELSAP hills out of service for 20-30 years. That is a 3500' lift, once you build a new liftline, acquire and install the lift, they'll be in for a million easy. Do the comparisons. We put in a 800' used T-bar on an existing liftline that cost $150,000. Act 250 permitting on cutting a new line would be a nightmare. Not to mention this would be a lift that starts nowhere and has no lapping ability. A project with very little/no ROI.