VTKilarney
Well-known member
They are still taking reservations for December 11th. What gives?
.
.
Welcome to AlpineZone, the largest online community of skiers and snowboarders in the Northeast!
You may have to REGISTER before you can post. Registering is FREE, gets rid of the majority of advertisements, and lets you participate in giveaways and other AlpineZone events!
Davis says he has twice threatened a work stoppage at Q Burke in the past three months, and this time he might have to pull the plug if he can’t get reassurances from the state soon. In recent weeks, he has paid subcontractors out of his own pocket “because they weren’t going to make their payroll.”
Late payments to subcontractors have also hurt the project’s budget, Davis says, because he has no choice but to impose a 12 percent late fee on Stenger and Quiros in order to cover the cost of the delays. Late fees will drive up the cost of the project by $100,000, Davis says.
The developers recommenced construction of the hotel and conference center, which had been halted in 2014. Once the developers met certain conditions in July, they also had permission to solicit more investors.
The developers need to attract, or “subscribe,” 196 investors to fully fund Q Burke. As of August, Q Burke had secured investments from 45 immigrants, or about $25 million, and the developers extended the subscription deadline from July 13 to Dec. 31 to attract more investors, documents show.
By October, 38 new immigrants seeking green cards had invested about $20 million in Q Burke.
The developers must hold the new money in a separate escrow account, and the funds can only be released after a third-party administrator signs off on construction expenditures. Ultimate authority for payment approvals rests with Donegan at DFR.
As of Sept. 9, the Q Burke brokerage account had insufficient funds to cover the July requisition payment for construction work to PeakCM, according to documents from DFR. It’s not clear how many new investors had subscribed at that juncture.
At the heart of the conflict is Donegan’s “serious concern” about the way the developers have represented the facts of the Q Burke project, “especially since DFR and ACCD received repeated assurances from you and the Principals that the project was abiding by all conditions and restrictions.”
“By the end of the week, I ask you to send me a full written explanation as to the raising and disbursement of the ______ capital,” Donegan writes. “In addition to providing the answer concerning the investor funds prior to July 15, 2015, the deliverables listed above must also be produced before I will consider any expense payments.”
They put out a call for local artists, craftsmen, etc early this past summer to submit their work for the new hotel. I submitted my photography for consideration but I have not heard a thing. Maybe they are waiting until the paint is dry before deciding what to hang on the wall?
The delays have disrupted the work flow and orders for materials, fixtures and furnishings have been put on hold, Stenger says.
They better start ordering up the "Pardon Our Appearance" signs soon for the first few weeks of guests if they still open the 11th......
Or at least order one and have Jr take pictures of it with his iPhone and print out duplicates.....
That's how I read it as well, although it was not clear.Trailboss- i read that a bit different. It said by August they had $25mm, and then by October they had 38 new investors. I inferred the "new" to update that August figure. In know Stenger was on a tear over in Vietnam or some such.
Trailboss- i read that a bit different. It said by August they had $25mm, and then by October they had 38 new investors. I inferred the "new" to update that August figure. In know Stenger was on a tear over in Vietnam or some such.
I also think the $190mm figure for Burke included the pie-in-the-sky aquatics and tennis center, The hotel alone is far less than that, so perhaps its fully funded (if my assumption above is correct).
Either way...my question now is... can Kingdom Trails run a ski area
Waiting to hear from Masskier to get his spin
Trailboss- i read that a bit different. It said by August they had $25mm, and then by October they had 38 new investors. I inferred the "new" to update that August figure. In know Stenger was on a tear over in Vietnam or some such.
I also think the $190mm figure for Burke included the pie-in-the-sky aquatics and tennis center, The hotel alone is far less than that, so perhaps its fully funded (if my assumption above is correct).
Either way...my question now is... can Kingdom Trails run a ski area
So the contractor is complaining about the state taking a long time to authorize the release of funds. Perhaps the contractor should be complaining about Stenger and Quiros, since the state only stepped in because of concerns about how the funds were being used.
So the contractor is complaining about the state taking a long time to authorize the release of funds. Perhaps the contractor should be complaining about Stenger and Quiros, since the state only stepped in because of concerns about how the funds were being used.